Your New Home Is Late? How Much the Developer Owes You in LAD and How to Claim in Malaysia 2026
Property Lab editorial teamPublished 9 min read

Key points
- In Malaysia, a developer that delivers a new home late under the Schedule G or H contract owes LAD of 10% a year of the SPA price, counted daily until vacant possession.
- KPKT's formula for LAD is days late × price × 10% ÷ 365, so a RM600,000 home delivered 180 days late earns about RM29,589 in Malaysia, on illustrative figures.
- LAD claims at Malaysia's Tribunal for Homebuyer Claims must be filed within 12 months of the CCC date, cost RM10 and are capped at RM50,000 unless both sides agree.
Contents
- How much LAD does a late developer owe in Malaysia?
- When does the LAD clock start and stop?
- What counts as delivery, and what does a late VP letter mean?
- Do condo buyers get LAD for late common facilities?
- How to claim LAD from a late developer in Malaysia: 5 steps
- What happens to LAD if the project is sick or abandoned?
- Frequently Asked Questions
If your new home is late in Malaysia, the developer owes you LAD (liquidated ascertained damages) of 10% a year of the purchase price, counted day by day from the delivery deadline until you take vacant possession. You can deduct it from what you still owe, or claim it at the Tribunal for Homebuyer Claims for up to RM50,000.
LAD = days late × SPA price × 10% ÷ 365. On a RM600,000 home, that is about RM164 for every day of delay.
The deadline is 24 months for landed homes and 36 months for strata homes, counted from the booking fee if you paid one. File a Tribunal claim within 12 months of the CCC date.
Key numbers (as at November 2026)
- LAD rate, counted daily10% a year
- Delivery period, landed (G)24 months
- Delivery period, strata (H)36 months
- Tribunal claim capRM50,000
- Tribunal window for LAD12 months from CCC
- Tribunal filing feeRM10
Also called: ganti rugi kelewatan penyerahan milikan kosong (KPKT's Malay term for LAD); liquidated ascertained damages or liquidated agreed damages; late delivery compensation; Tribunal Tuntutan Pembeli Rumah or TTPR (Tribunal for Homebuyer Claims); Lanjutan Masa or EOT (extension of time); Perakuan Siap dan Pematuhan or CCC (Certificate of Completion and Compliance).
How much LAD does a late developer owe in Malaysia?
Under clause 24(2) of Schedule G and clause 25(2) of Schedule H, a Malaysian developer that delivers late pays LAD at 10% a year of the purchase price, calculated from day to day. The count runs from the end of the delivery period until the date you take vacant possession.
The KPKT tribunal FAQ gives the formula as days late × house price × 10% ÷ 365. Its own example: a RM300,000 house handed over 100 days late earns RM8,219.18.
Illustrative LAD on a RM600,000 SPA price, our sums. The cap limits one Tribunal claim, not what the developer owes.
| Days late | LAD on RM600,000 | Within Tribunal cap? |
|---|---|---|
| 90 | RM14,794.52 | Yes |
| 180 | RM29,589.04 | Yes |
| 365 | RM60,000 | No |
Illustrative, worked out in Python: RM600,000 × 10% ÷ 365 = RM164.38 a day. At this price the RM50,000 cap is passed on day 305. On any price above RM500,000, a full year of delay is worth more than the cap.
Use the price written in the SPA. In Sri Damansara v Voon Kuan Chien, the Court of Appeal refused the developer's bid to count LAD on a discounted price, says a PKNS legal note on the case.
What this means: settle the price and the start date first, as they move the answer most.
Source: KPKT, TTPR FAQ; P.U.(A) 106/2015 gazette; PKNS legal note
When does the LAD clock start and stop?
In Malaysia the LAD clock starts when the 24-month (landed) or 36-month (strata) delivery period ends, and the standard contracts count that period "from the date of this Agreement". Courts have moved the start earlier where a booking fee was paid.
- Booking fee date: in PJD Regency v Tribunal Tuntutan Pembeli Rumah (2021), the Federal Court held that the period runs from the booking fee or a written intention to buy, not the SPA date. Regulation 11(2) bars developers from collecting such fees.
- Controller's extensions: in Ang Ming Lee (26 November 2019), the Federal Court ruled that the Controller of Housing had no power to extend the period, as regulation 11(3) was ultra vires the Act.
- Older extensions: in Obata-Ambak v Prema Bonanza (26 July 2024), the Federal Court said Ang Ming Lee applies prospectively, so extensions granted before it remain valid.
- The Minister: in Bludream City (2022), the Court of Appeal held that the Minister himself may still extend the period.
The clock stops on the day you take vacant possession. Under clause 26(3) of Schedule G and 27(3) of Schedule H, that happens anyway 30 days after the developer's notice, whether or not you collect the keys.
- 1 Mar 2023Booking fee paid36 months start here (PJD Regency)
- 1 Jun 2023SPA signedDeadline would be 1 Jun 2026 from this date
- 1 Mar 2026Delivery deadline passesLAD starts the next day
- 14 Aug 2026CCC issuedTribunal window opens
- 28 Aug 2026Buyer takes vacant possessionLAD stops after 180 days
- 14 Aug 2027Last day to file at the Tribunal12 months from the CCC
Invented dates for a strata unit, to show the counting. Your SPA, receipts and CCC give the real dates.
| Illustrative strata unit | Days late | LAD on RM600,000 |
|---|---|---|
| Counted from booking fee | 180 | RM29,589.04 |
| Counted from SPA date | 88 | RM14,465.75 |
Dates are made up for the example: booking fee 1 March 2023, SPA 1 June 2023, vacant possession taken 28 August 2026. The gap of RM15,123.29 is our calculation. Check TEDUH and your SPA for any approved extension before you count.
Keep your booking fee receipt and any written offer to buy: under PJD Regency, they can move your start date earlier.
Source: Allen & Gledhill on PJD Regency, Feb 2021; Allen & Gledhill on Ang Ming Lee; EdgeProp, 26 Jul 2024; Allen & Gledhill on Bludream City
What counts as delivery, and what does a late VP letter mean?
A Malaysian developer has delivered on time only if vacant possession comes "in the manner stipulated" in the contract, so a letter alone does not stop LAD. Clause 26(1) of Schedule G and 27(1) of Schedule H list the conditions.
- CCC issued: the Certificate of Completion and Compliance must be out first.
- Utilities ready: water and electricity must be ready for connection.
- Strata title (Schedule H): your unit's strata title must be issued, unless the Controller certifies a handover without it.
- Your side: you must have paid what is due under the SPA.
No power, no proper handover: in Remeggious Krishnan v SKS Southern (6 March 2023), the Federal Court held that "ready for connection" means actual supply. HBA writers note the court treated late delivery as an LAD matter and a faulty handover as a claim for compensatory damages.
A late VP letter is a notice to take possession sent after the deadline. LAD runs up to the day you take possession, so keep the dated envelope, the notice and your key collection form.
Late title: once the title is registered in your name, the developer must hand you the original within 30 days. Missing that date triggers LAD at the same 10% rate (clause 13(4) G, 28(4) H).
Vacant Possession in Malaysia: Meaning, CCC and What to Check covers key collection day in detail.
Source: JPN, Schedules G and H via the Akta page; EdgeProp (HBA), Sep 2024
Do condo buyers get LAD for late common facilities?
Yes. Clause 29 of Schedule H gives Malaysian strata buyers a second LAD claim when the common facilities are not finished within 36 months of the agreement, separate from the LAD on the unit itself.
- Rate: 10% a year, but only on the last 20% of the purchase price.
- Timing: your claim accrues once the facilities are completed and certified.
Illustration: on a RM600,000 unit the base is RM120,000, so the rate works out at RM32.88 a day, or RM5,917.81 for 180 days late, on our sums. Landed Schedule G has no matching clause.
Source: Schedule H clause 29, P.U.(A) 106/2015
How to claim LAD from a late developer in Malaysia: 5 steps
- Work out the figure: count the days from your deadline to the day you took possession, then apply the formula to the SPA price. Keep the booking receipt.
- Write to the developer: send your calculation and a written demand, by registered post as the SPA's notice clause allows, and keep proof of posting.
- Deduct it: clause 25(3) of Schedule H (24(3) of G) says LAD is payable right after the VP notice; if unpaid, you may deduct it from any instalment due. Ask your lawyer and bank to arrange this.
- File at the Tribunal: submit four copies of Borang 1 with the SPA, the VP letter and the CCC, plus the RM10 fee, within 12 months of the CCC date.
- Go to court for more: a claim above RM50,000 goes to the Sessions Court, unless both sides agree in writing to use the Tribunal.
After filing, you serve the sealed Borang 1 on the developer and give a copy to your bank; the developer then has 14 days to file its defence. Lawyers need the Tribunal's leave, says KPKT's Borang 1 page.
Key insight: the Tribunal deadline for LAD runs from the CCC, not from your keys. If handover drags on after the CCC, that 12-month window keeps shrinking while LAD is still adding up, so file early.
Court claims face the six-year limit in section 6 of the Limitation Act 1953. The 2015 contracts say an LAD claim accrues when you take vacant possession, but in Obata-Ambak the Federal Court counted from the 2012 SPAs, Azmi & Associates explain. Do not wait for years.
What happens to LAD if the project is sick or abandoned?
If a Malaysian housing project is abandoned, the Tribunal for Homebuyer Claims cannot hear it: KPKT lists abandoned projects among the claims outside its jurisdiction. Your routes then are the Act, the Housing Development Account and the courts.
- Terminate: section 8A of Act 118 lets you end the SPA if work stops for 6 months or more, with your end financier's written consent and the Controller's certificate. The developer must refund all your money, without interest, within 30 days.
- Tribunal awards: under a 2015 amendment, the Controller may use money in the project's Housing Development Account to comply with a Tribunal award.
- Check status: KPKT says its TEDUH portal shows projects classed as late, sick or abandoned, and approvals such as extensions of time.
What this means: on our reading of the contracts, a sick project that is finished late is an ordinary LAD case, while one that stops needs a lawyer. 6 Checks Before Buying a New Launch: How to Avoid Abandoned Projects in Malaysia explains the warning signs.
Source: KPKT tribunal FAQ, items 4 and 10; JPN: Act A1415 and the 2015 account rules; Bernama, 7 Sep 2026
Frequently Asked Questions
How is LAD calculated in Malaysia?
Multiply the days of delay by the SPA price, take 10% of that and divide by 365. KPKT's example of RM300,000 and 100 days gives RM8,219.18.
How do I claim LAD from a developer?
Send a written demand with your figures. If it is not paid, deduct it from an instalment you still owe, or file Borang 1 at the Tribunal within a year of the CCC.
Can I claim LAD at the Tribunal for Homebuyer Claims?
Yes, for homes in Peninsular Malaysia and Labuan. Each claim is capped at RM50,000, and the fee is RM10.
Does the delivery period start from the booking fee or the SPA?
From the booking fee, where one was paid, following the Federal Court in PJD Regency. Otherwise it runs from the SPA date.
Is LAD still payable if the developer got an extension of time?
It depends on who granted it and when. The Controller lost that power in Ang Ming Lee, though extensions it gave earlier still stand, and the Court of Appeal accepts extensions by the Minister.
What if my LAD is more than RM50,000?
Sue in the Sessions Court, or agree in writing with the developer to let the Tribunal decide the full amount.
Does LAD keep running if I delay collecting my keys?
Only up to the deemed handover. Thirty days after a valid notice you are treated as having taken possession, so waiting longer adds no days.
Do I get LAD for late repairs during the defect liability period?
No, LAD covers late handover. Defects follow their own 30-day repair rules; see Defect Liability Period in Malaysia: 24 Months and How to Claim.
Contracts, tribunal rules and case law change, so check the latest wording with KPKT, JPN and your own SPA before you claim.
This page is general information, not legal or financial advice. The worked examples use invented dates and prices. Ask a lawyer before you deduct money from an instalment or sue a developer.
Sources
- Soalan Lazim - Tribunal Tuntutan Pembeli Rumah — Kementerian Pembangunan Kerajaan Tempatan (KPKT)
- Housing Development (Control and Licensing) (Amendment) Regulations 2015, P.U.(A) 106/2015 — Attorney General's Chambers, published by Jabatan Perumahan Negara
- Permohonan Borang Tuntutan oleh Pembeli Rumah (Borang 1) — Kementerian Pembangunan Kerajaan Tempatan (KPKT)
- Federal Court holds date of calculation of liquidated agreed damages begins from date of payment of booking fee — Allen & Gledhill
- Malaysian Federal Court rules Controller of Housing had no right to grant extension of time to developers — Allen & Gledhill
- Apex court rules Ang Ming Lee housing decision is to be applicable prospectively, not retrospectively — EdgeProp.my
General information only, not legal, tax or investment advice. Rules and rates change; check the official source linked below before you act.
Homes on Property Lab
Related news
Related guides
Defect Liability Period in Malaysia: 24 Months and How to Claim
Vacant Possession in Malaysia: Meaning, CCC and What to Check
Booking Fee Paid, Then Changed Your Mind? 5 Refund Rules in Malaysia
Property Deal Too Good to Be True? 7 Scam Signs to Check in Malaysia
Can You Keep a Dog or Cat in a Malaysian Condo? Pet Rules and 6 Checks